Grid Interconnection Queue Statistics 2026

Axis Intelligence Research  ·  Aidan Jad  ·  July 29, 2026  ·  CC BY 4.0
GQBWR™ 2025 Baseline · 14.2×
2,061 GW
Active U.S. queue capacity end-2025 · 8,200 projects · 1.5× total U.S. installed generating fleet · LBNL Queued Up 2026
14.2×
GQBWR™ 2025 baseline — for every 1 GW built, ~14 GW withdrew · Axis Intelligence Research proprietary metric · formula: GW withdrawn ÷ GW reaching COD
61 mo.
Median wait time (IR to COD) for projects completing in 2025 · up from 22 months in 2008 · 177% increase · LBNL Queued Up 2026
13%
Completion rate by capacity (2000–2020 cohort) · 75% withdrawn · 22,061 requests studied · LBNL Queued Up 2026 Edition
2,500+ GW
Global grid queue backlog · renewable + large-load + storage projects stalled worldwide · IEA Electricity 2026 · Grid connection queues at record levels
GQBWR™ — Grid Queue Build-vs-Withdraw Ratio — Axis Intelligence Research — Baseline July 29, 2026
~4×
est. 2010–2015
~8×
est. 2019–2022
14.2×
2025 — baseline reading
Formula: GQBWR = GW withdrawn in year ÷ GW reaching commercial operation in year
2025 inputs: ~750 GW withdrawn (LBNL lower bound) ÷ ~53 GW reaching COD (2% throughput rate from 2,290 GW prior-year active base)
GQBWR 2025 = 750 ÷ 53 = 14.2× — Axis baseline July 29, 2026
Interpretation: A ratio above 10× signals that the interconnection process functions primarily as an attrition mechanism. For every GW delivered to the grid in 2025, roughly 14 GW abandoned the attempt. A ratio converging toward 1× would indicate a functioning, throughput-oriented process.
2010–15
~4×
2016–18
~6×
2019–22
~8×
2023–24
~11×
2025
14.2×
Data sources: LBNL Queued Up 2026 Edition (emp.lbl.gov/queues), June 2026 — covering 7 ISOs/RTOs + 50 non-ISO balancing areas representing ~98% of U.S. installed generating capacity. Pre-2025 GQBWR values are Axis Intelligence Research estimates derived from LBNL historical inflow/outflow data; 2025 is the first year computed with published annual COD figures. Note: withdrawn-year data available for only 63% of withdrawn requests (LBNL data gap); 750 GW is LBNL's stated lower bound.
Median Wait Time IR to COD (months) — Projects Completing That Year
Source: LBNL Queued Up 2026 Edition · Sample: 3,310 projects from 6 ISOs + 19 non-ISO BAs with valid COD dates · IR = Interconnection Request · COD = Commercial Operations Date
Active Queue by Resource Type — GW (End 2025)
Source: LBNL Queued Up 2026 Edition · YoY changes: Solar −19% · Storage −16% · Gas +86% · Wind −19% · Nuclear +96% · Geothermal +170%
U.S. Active Queue Capacity Trend (GW) — 2019–2025
Source: LBNL Queued Up editions 2020–2026 · Peak 2023: ~2,600 GW · 2024: ~2,290 GW · 2025: 2,061 GW (−10% YoY) · Note: decline driven by accelerated withdrawals, not accelerated delivery
Completion Rate by Region (2000–2020 Cohort, by Capacity)
Source: LBNL Queued Up 2026 Edition · 21,927 requests · 3,501 GW cohort · ERCOT only region exceeding 20% · CAISO 8% · Non-ISO West 10%
Active Queue by ISO/Region — GW (End 2025)
Source: LBNL Queued Up 2026 Edition, slide 13 · ERCOT only region growing in 2025 · West (non-ISO) largest by volume (solar + geothermal dominated) · Bars scaled to West = 100%
Queue Inflow vs Outflow — 2025 (GW)
Source: LBNL Queued Up 2026 Edition slide 12 · Annual throughput rate: 53 ÷ 2,290 = 2.3% · Withdrawn capacity estimated at lower bound · Note: withdrawal-year data available for 63% of withdrawn requests
ISO/RTO Interconnection Reform Status — Mid-2026
ISO / Region Active GW Queue Status Key Reform (2025–2026) Fast-Track
Sources: LBNL Queued Up 2026 Edition (slide 10) · FERC "Energized for 2026" (ferc.gov, Jan 14 2026) · CAISO Cluster 16 Oct 2026 · SPP Consolidated Planning Process Mar 2026 · NYISO first cluster Jul 31 2026 · MISO SUGAR pilot: 98% study time reduction
Median IR-to-COD Duration by Project Size (months)
Source: LBNL Queued Up 2026 Edition slide 54 · 20 MW = FERC LGIP/SGIP threshold · Median LGIP duration is ~2× SGIP · All utility-scale data center generation exceeds 20 MW threshold
Gas vs Renewables Queue Composition — 2024 vs 2025 (GW)
Source: LBNL Queued Up 2025 + 2026 Editions · Gas: +86% YoY (136 → 253 GW) · Solar: −19% (956 → 773 GW) · Storage: −16% (890 → 749 GW) · Wind: −19% (271 → 220 GW)
Key Data Points — Axis Intelligence Research Findings & LBNL Primary-Source Statistics