Nuclear Energy for Data Centers 2026: 14.1 GW of Big Tech Nuclear Deals Tracked, and What Actually Reaches the Grid in 2027

Nuclear energy for data centers 2026: Amazon, Google, Meta and Microsoft hold 14,103 MW of nuclear contracts, with 835 MW of new capacity due by 2027

Nuclear Energy for Data Centers 2026

By Axis Intelligence Research

Co-author: Aidan Jad | Last updated: November 3, 2026 | License: CC BY 4.0

Amazon, Google, Meta and Microsoft now hold 14,103 MW of nuclear capacity under contract or development agreements, according to a deal-by-deal ledger compiled by Axis Intelligence Research from company and regulatory filings as of November 3, 2026. Only 7,879 MW of that is new capacity for the grid, and just 835 MW of the new capacity is scheduled to arrive before the end of 2027.


Quick Answer

As of November 3, 2026, Axis Intelligence Research counts 14,103 MW of nuclear capacity tied to Amazon, Google, Meta and Microsoft across 16 contracted blocks. 44.1% comes from reactors already running. The Crane (Three Mile Island Unit 1) restart for Microsoft is the only new nuclear capacity scheduled for 2027. No small modular reactor is scheduled to deliver power to a hyperscaler before 2030.

Key Findings

  1. Axis Intelligence Research counts 14,103 MW of nuclear capacity contracted by Amazon, Google, Meta and Microsoft as of November 3, 2026, built from 16 deal blocks disclosed in company and regulatory filings.
  2. 6,224 MW, or 44.1% of that total, is output from reactors that were already operating: the contracts keep plants licensed and running but add no new megawatts to the grid, per the Axis Intelligence Research ledger.
  3. The Axis Nuclear Offtake Maturity Index (NOMI) reads 65.0 out of 100 for all contracted capacity and 37.4 for new-to-grid capacity, as of November 3, 2026.
  4. Only 835 MW of new nuclear capacity tied to a hyperscaler, the Crane restart contracted by Microsoft, is scheduled to reach the grid by the end of 2027: 10.6% of the 7,879 MW of new capacity in the ledger.
  5. Meta holds 7,730 MW, or 54.8% of all hyperscaler nuclear capacity in the Axis Intelligence Research ledger, more than Amazon, Google and Microsoft combined.

How Much Nuclear Power Have Big Tech Companies Contracted for Data Centers?

The answer is 14,103 MW across four buyers, and the number only means something once you split it by what physically happens at the plant.

Axis Intelligence Research rebuilt the count from the original press releases and filings of the power sellers, not from aggregator tallies. Each row below is a block of capacity a named company has disclosed, with the megawatts it disclosed. Where a deal mixes existing output and new uprate capacity, the two are split into separate rows so nothing is counted twice.

Hyperscaler nuclear deal ledger (as of November 3, 2026)

BuyerSeller / developerAssetTypeMWFirst scheduled deliverySource
MetaVistraPerry and Davis-BesseExisting output2,176Late 2026Vistra
MetaVistraPerry, Davis-Besse, Beaver ValleyUprates433Added through 2034Vistra
MetaConstellationClintonExisting output1,121June 2027Constellation
MetaTerraPowerUp to 8 Natrium unitsNew build2,800As early as 2032TerraPower
MetaOkloPike County, Ohio campusNew build1,200Phase 1 as early as 2030Oklo
AmazonTalen EnergySusquehannaExisting output1,920Ramping; full volume by 2032Talen Energy
AmazonConstellationCalvert CliffsExisting output500Not disclosedConstellation
AmazonConstellationCalvert CliffsUprate1902030–2032Constellation
AmazonX-energy / Energy NorthwestCascade Xe-100, phase 1New build320Early 2030sX-energy S-1/A
GoogleConstellation11 units in IL, PA, NJUprates890First by 2028; all before end-2032Constellation
GoogleNextEra EnergyDuane ArnoldRestart615Q1 2029NextEra Energy
GoogleFortumLoviisa, Finland (up to 50%)Existing output5072028; 50% from 2030Fortum
GoogleKairos PowerKP-FHR fleet (balance)New build450By 2035Kairos Power
GoogleGeorgia PowerVogtle 1–2, Hatch 1–2 (pending PSC)Uprates96Not disclosedGeorgia Power
GoogleKairos Power / TVAHermes 2New build502030NRC
MicrosoftConstellationCrane (Three Mile Island Unit 1)Restart8352027Constellation
Total14,103Axis Intelligence Research

All MW are company-reported. Loviisa: Fortum’s release states two 507 MWe reactors and a contract for up to 50% of capacity; Axis Intelligence Research converts that to 507 MW. Kairos: the 500 MW Google agreement is split into Hermes 2 (50 MW, which holds NRC construction permits) and the remaining 450 MW. Calvert Cliffs: Constellation’s 690 MW contract includes the 190 MW uprate, so existing output is 500 MW.

What the ledger deliberately leaves out

Four announcements are not in the 14,103 MW, because counting them would inflate the number. Amazon’s option-based target of more than 5 GW of Xe-100 projects by 2039 is a framework, and its first project (Cascade) is already in the ledger, per X-energy’s April 2026 S-1/A filing. Google’s separate 15-year agreement for 2,700 MW from Constellation’s PJM fleet is not nuclear-specific in Constellation’s release. Oracle will subscribe to “a portion” of the Point Beach Nuclear Plant energy that We Energies is required to buy, an agreement the utility expects to save its customers about $300 million in fuel costs, per We Energies on October 2, 2026; the release gives no megawatt figure, and full details go to the Public Service Commission of Wisconsin in the coming months. And the 890 MW Google uprate total is counted once, even though Constellation’s own DOE loan release later folded it into a combined figure.

Aidan Jad’s read: a headline gigawatt number that mixes these categories tells a buyer nothing about when power shows up. The ledger is built so every row can be dated.

How Much of Big Tech’s Nuclear Is New Capacity?

7,879 MW, or 55.9% of the ledger, would be new capacity on the grid. The other 6,224 MW (44.1%) is output from reactors that were already operating before the contract was signed.

Deal typeMWShare of ledgerWhat it means at the plant
Existing output6,22444.1%Contract for power from running reactors; supports relicensing
New build (SMR / advanced)4,82034.2%Reactors that do not yet exist
Uprates1,60911.4%Turbine, generator and steam-path upgrades on running units
Restarts1,45010.3%Shut reactors returned to service
Total14,103100%

Source: Axis Intelligence Research ledger, as of November 3, 2026. Formula: category MW ÷ 14,103 × 100.

The existing-output contracts are not empty. Vistra says its Meta agreements give it the certainty to pursue subsequent license renewals at Perry, Davis-Besse and Beaver Valley, and Constellation says the Clinton contract takes over when Illinois’s ratepayer-funded zero emission credit program expires in mid-2027. Keeping a 1,121 MW reactor online is real capacity protection. It is still not an extra megawatt for a grid operator that is short of supply.

The fastest new megawatts are coming from the least glamorous line in the table. Uprates and restarts add 3,059 MW combined, all at sites that already hold a license, a transmission connection and a trained workforce. Constellation reports that its Google and Amazon agreements incentivize more than $7 billion of investment to add about 1,080 MW of nuclear capacity, and on October 27, 2026 it announced a conditional U.S. Department of Energy loan commitment of up to $5 billion for uprates at eight of its plants, per Constellation.

Which company has contracted the most nuclear power?

BuyerContracted MWNew-to-grid MWShare of ledgerNOMI reading
Meta7,7304,43354.8%56.6
Amazon2,93051020.8%89.2
Google2,6082,10118.5%61.1
Microsoft8358355.9%70.0

Source: Axis Intelligence Research ledger and NOMI, as of November 3, 2026.

The two numbers pull in opposite directions, and that is the useful part. Amazon’s portfolio is the most mature (89.2) because 2,420 of its 2,930 MW come from running reactors at Susquehanna and Calvert Cliffs, but only 510 MW of it is new. Google has the highest share of new capacity: 2,101 of 2,608 MW (80.6%) is restarts, uprates or new builds. Meta has the most megawatts and the most exposure to designs that are not yet built: 4,000 MW sits with TerraPower and Oklo.

Which Nuclear Megawatts Reach Data Centers in 2027?

On contract dates alone, 4,132 MW of the ledger is scheduled to start delivering by the end of 2027, and only 835 MW of that is new capacity.

DealMWScheduled startNew capacity?
Meta – Vistra (Perry, Davis-Besse)2,176Late 2026No
Meta – Constellation (Clinton)1,121June 2027No
Microsoft – Constellation (Crane restart)8352027Yes
Amazon – Talen (Susquehanna)Ramp volume for 2027 not disclosedIn progressNo
Dated total by end-20274,132835 new

Sources: Vistra (January 9, 2026); Constellation (June 3, 2025); Constellation Crane Clean Energy Center page; Talen Energy (June 11, 2025). Talen discloses 840–1,200 MW of deliveries in 2029 and the full 1,920 MW no later than 2032, so 2027 volume is excluded rather than estimated.

Crane is the hinge of 2027. Microsoft’s 20-year contract covers the plant’s roughly 835 MW, and Constellation’s September 2024 release targeted 2028. Constellation now says it expects the plant to be ready for service in 2027, per its Crane Clean Energy Center page. The U.S. Department of Energy closed a $1 billion loan to Constellation for the restart on November 18, 2025, with the restart still pending NRC licensing approvals.

Aidan Jad’s read: a restart is the closest thing nuclear has to a known quantity. The reactor vessel, the license history and the grid tie already exist; the schedule risk lives in the interconnection queue and the turbine hall, not in a first-of-a-kind design. If Crane slips into 2028, the 2027 count of new hyperscaler nuclear capacity drops to zero.

What comes after 2027?

Scheduled first deliveries for new capacity, from the same filings:

  • 2028: the first Constellation uprate for Google, per Constellation; Fortum’s Loviisa contract with Google starts at a reduced volume (existing output, not new).
  • 2029: Duane Arnold restart, 615 MW, targeted for Q1 2029 by NextEra Energy.
  • 2030: Kairos Power’s 50 MW Hermes 2 for the TVA grid serving Google; Oklo’s first Pike County phase “as early as 2030”; Calvert Cliffs uprate window opens (2030–2032).
  • 2032: TerraPower’s first Natrium units for Meta “as early as 2032”; Google’s full 890 MW of Constellation uprates “before the end of 2032.”
  • 2034–2035: Vistra’s 433 MW of uprates fully online by 2034; Oklo’s full 1.2 GW by 2034; Kairos Power’s 500 MW by 2035.

Cascade (320 MW) and Georgia Power’s 96 MW have no in-service date in their primary documents. X-energy’s S-1/A says the Cascade construction permit application is targeted for NRC submission by the end of 2026, with a permit anticipated in 2028 and commercial operation in the early 2030s.

The Axis Nuclear Offtake Maturity Index (NOMI)

The Axis Nuclear Offtake Maturity Index (NOMI) measures how far a portfolio of contracted nuclear megawatts is from physical delivery, on a 0–100 scale. A reading of 100 means every contracted megawatt comes from a reactor already generating; a reading near 10 means the capacity depends on designs with no commercial license application on file.

NOMI formula and stage weights

NOMI = Σ(MW × stage weight) ÷ Σ(MW) × 100

StageDefinitionWeightMW in ledger
AOutput from an operating reactor1.006,224
BRestart of a shut reactor0.701,450
CUprate at an operating reactor0.601,609
DNew unit that holds an NRC construction permit0.4050
ENew unit whose design’s lead commercial project holds an NRC construction permit or a docketed permit application0.253,120
FNew unit with no docketed commercial application for its design0.101,650

Stage evidence: Hermes 2 construction permits issued November 21, 2024 (NRC); Kemmerer Unit 1 (Natrium) construction permit authorized March 4, 2026 (NRC); Long Mott (Xe-100) permit application docketed May 2025 per X-energy’s S-1/A; Oklo Aurora in NRC pre-application review (NRC). Kairos KP-FHR commercial fleet beyond Hermes 2 placed at stage F because no commercial permit application was found.

NOMI readings, November 3, 2026 (baseline)

  • All contracted capacity: 65.0. Calculation: (6,224 × 1.00 + 1,450 × 0.70 + 1,609 × 0.60 + 50 × 0.40 + 3,120 × 0.25 + 1,650 × 0.10) ÷ 14,103 × 100 = 9,169.4 ÷ 14,103 × 100.
  • New-to-grid capacity only: 37.4. Calculation: 2,945.4 ÷ 7,879 × 100.

This is the baseline reading. Axis Intelligence Research will recompute NOMI when a contract is signed, when a project moves stages (a permit, a restart, a commercial operation date), or quarterly, whichever comes first.

What would move the number: Crane returning to service in 2027 lifts its 835 MW from weight 0.70 to 1.00 and adds about 1.8 points to the all-capacity reading (835 × 0.30 ÷ 14,103 × 100). A docketed construction permit application for a Meta Natrium site would not move TerraPower’s stage, because the design already holds a permit at Kemmerer; a permit for the Meta units themselves would. NOMI weights the regulatory and physical status of each block. It does not price contract terms, which are confidential in almost every deal on this page, and it treats a megawatt in Finland the same as one in Ohio.

Why Do Data Centers Want Nuclear Instead of More Solar and Wind?

Because the capacity factor gap is the business case. U.S. nuclear plants ran at a 91.1% capacity factor in 2025, against 33.8% for wind and 24.0% for utility-scale solar PV, per the U.S. Energy Information Administration’s Electric Power Annual Table 4.08.B.

SourceCapacity factor 2025Capacity factor 2024Source
Nuclear91.1%90.8%EIA Table 4.08.B
Natural gas combined cycle58.7%60.5%EIA Table 4.08.A
Coal48.8%n/aEIA Table 4.08.A
Wind33.8%34.3%EIA Table 4.08.B
Solar photovoltaic24.0%23.2%EIA Table 4.08.B

Capacity factor: the electricity a plant actually produced in a year divided by what it would have produced running at full output every hour.

A data hall drawing 100 MW around the clock needs 876 GWh a year. Supplying that from a solar array running at 24.0% takes roughly 417 MW of panels plus storage to move the energy into the night; from nuclear at 91.1%, about 110 MW of reactor share (876,000 MWh ÷ 8,760 h ÷ capacity factor). The math is why hyperscalers keep signing both: solar for cheap energy, nuclear for the hours solar cannot cover.

How much electricity could the contracted nuclear capacity supply?

Axis Intelligence Research estimates that the 13,596 MW of U.S. capacity in the ledger (14,103 MW minus Loviisa’s 507 MW) would generate about 108.5 TWh a year at the 2025 U.S. nuclear capacity factor of 91.1%. Formula: 13,596 MW × 8,760 hours × 0.911 ÷ 1,000,000.

That is equal to 61.6% of the 176 TWh U.S. data centers consumed in 2023, per Lawrence Berkeley National Laboratory’s report for the U.S. Department of Energy. It is an upper bound: it assumes every contracted megawatt is built and runs at today’s fleet average, and the same LBNL report projects U.S. data centers reaching 6.7% to 12% of national electricity use by 2028, up from 4.4% in 2023. For the latest consumption figures, see the Axis AI data center energy consumption statistics and the data center electricity demand tracker.

How Much Data Center Electricity Comes From Nuclear Today?

About 15% globally and around 20% in the United States, per the International Energy Agency’s Energy and AI report. The IEA measures the fuel mix of electricity physically consumed by data centers on their local grids, not the contracts their operators sign.

RegionNuclear share of data center electricityLargest sourceSource
World15%Coal, about 30%IEA, Energy and AI
United StatesAround 20%Natural gas, over 40%IEA, Energy and AI

The IEA’s Base Case puts global electricity generation for data centers at 460 TWh in 2024, over 1,000 TWh in 2030 and 1,300 TWh in 2035, with small modular reactors entering the supply mix after 2030. The agency also says technology companies have plans to finance more than 20 GW of SMRs. The Axis ledger counts 4,820 MW of hyperscaler new-build nuclear with named developers and megawatt figures: a quarter of that IEA figure, which suggests most of the 20 GW is still at the plan stage rather than under a signed, sized agreement.

Note on demand figures: the IEA’s 460 TWh is generation supplied to data centers. Figures for data center electricity consumption elsewhere in the same IEA report are a different measure and are not interchangeable with it.

Are Small Modular Reactors Ready to Power Data Centers?

Not before 2030 on any schedule in the primary documents. No SMR in the ledger has an NRC operating license, and only one contracted unit, Kairos Power’s 50 MW Hermes 2, holds an NRC construction permit.

DesignDeveloperHyperscalerNRC status (as of Nov. 2026)Earliest delivery stated
Natrium (345 MWe)TerraPowerMetaKemmerer Unit 1 construction permit authorized March 4, 2026As early as 2032 (Meta units)
KP-FHR / Hermes 2Kairos PowerGoogleHermes 2 construction permits issued Nov. 21, 20242030
Xe-100X-energyAmazonDow Long Mott application docketed May 2025; Cascade application targeted end-2026Early 2030s
Aurora (up to 75 MWe)OkloMetaPre-application with NRCAs early as 2030

Sources: NRC news release 26-028; NRC Hermes 2 project page; X-energy Form S-1/A (April 20, 2026); NRC Oklo pre-application page; TerraPower; Kairos Power; Oklo.

The NRC called Kemmerer Unit 1 the first commercial reactor it had approved for construction in nearly a decade, and the U.S. Department of Energy expects the plant to be complete in 2030. That plant serves PacifiCorp’s grid, not a Meta data center; Meta’s Natrium units are follow-on plants whose first site TerraPower said it would identify after the January 2026 agreement.

Aidan Jad’s read: the order book is ahead of the license book. 4,820 MW of SMR and advanced-reactor capacity is contracted to hyperscalers, and 50 MW of it holds a construction permit. That is the gap to watch in 2027, more than any new announcement.

What Federal Policy Is Driving Nuclear for Data Centers?

Executive Order 14302, signed May 23, 2025, directs the Department of Energy to facilitate 5 GW of power uprates at existing reactors and to have 10 new large reactors with complete designs under construction by 2030, per the White House.

The hyperscaler ledger already covers 1,609 MW of uprates, about a third of that 5 GW national target (1,609 ÷ 5,000 = 32.2%). It contains no new large reactors. The federal loan program has followed the uprate path: the conditional commitment of up to $5 billion announced by Constellation on October 27, 2026 is for uprates, not new units.

On the customer side, grid costs are the political constraint. Constellation describes the Google agreement as a response to PJM’s “Bring Your Own Power” proposal for large loads, and Georgia Power says Google’s uprate subscription is structured so other customers do not carry the incremental cost. Axis Intelligence Research tracks the household side in data centers and electricity bills by state and the industrial side in data center electricity cost by state.

FAQ: Nuclear Power for Data Centers

Does a nuclear power purchase agreement mean the data center runs on nuclear electrons?

Usually not directly. In most deals on this page, the reactor’s output flows to the regional grid and the buyer pays for the energy or its clean attributes; Constellation says all Calvert Cliffs output keeps flowing to the PJM grid under the Amazon contract. Talen’s Susquehanna contract with Amazon moved from a co-located arrangement to a grid-connected (“front-of-the-meter”) structure.

Why are nuclear uprates suddenly the cheapest new nuclear for AI?

An uprate raises the output of a reactor that is already licensed and connected, so it skips site permitting and new transmission. The ledger holds 1,609 MW of uprates, and Constellation reports more than $4.3 billion of investment for the 890 MW backed by Google, which works out to roughly $4.8 million per MW on company-reported figures ($4.3 billion ÷ 890 MW).

Is the Three Mile Island (Crane) restart still on schedule for 2027?

Constellation says it expects the plant to be ready for service in 2027, pending NRC licensing approvals. The 835 MW plant has a 20-year contract with Microsoft and a $1 billion DOE loan closed on November 18, 2025. It is the only new hyperscaler nuclear capacity in the Axis ledger scheduled for 2027.

When will the first small modular reactor power a Big Tech data center?

No earlier than 2030 on current schedules. Kairos Power’s 50 MW Hermes 2, whose output goes to the Tennessee Valley Authority grid under an agreement backed by Google, is scheduled for 2030 and is the only contracted unit holding an NRC construction permit as of November 2026.

Which tech company has the most nuclear power contracted?

Meta, with 7,730 MW across Vistra, Constellation, TerraPower and Oklo, or 54.8% of the Axis Intelligence Research ledger. Meta’s own “up to 6.6 GW” figure covers only its January 2026 agreements with Vistra, TerraPower and Oklo; the 1,121 MW Clinton contract with Constellation is separate.

How reliable is nuclear compared with gas for a 24/7 data center?

U.S. nuclear plants averaged a 91.1% capacity factor in 2025, against 58.7% for natural gas combined-cycle plants, per EIA. Gas plants run less because they are dispatched to follow demand, so the gap reflects operating pattern as well as availability.

How do I reproduce the NOMI score?

Download the CSV, multiply each deal row’s value (MW) by its nomi_weight, sum the results, divide by total MW and multiply by 100. The all-capacity baseline reading is 65.0; restricting to rows where new_to_grid = yes gives 37.4.

Methodology

Scope. The ledger includes nuclear capacity that Amazon, Google, Meta or Microsoft has contracted or funded through a disclosed agreement naming a counterparty and a megawatt figure. Oracle, colocation providers and AI developers are excluded from this edition because their agreements are pending, unsized or not nuclear-specific in primary documents.

Collection. Every megawatt figure was read from the seller’s, developer’s or regulator’s own release or filing on November 3, 2026. Aggregator trackers and media tallies were used only to find deals; no figure on this page comes from them.

Splitting rules. Contracts that combine existing output and uprates are split (Calvert Cliffs 500 + 190; Vistra 2,176 + 433). Clinton’s 1,121 MW is kept as one row because Constellation does not state whether it includes the 30 MW uprate. Loviisa is converted from “up to 50%” of two 507 MWe units to 507 MW. Kairos is split into Hermes 2 (50 MW) and the remaining 450 MW.

Exclusions. Framework targets (Amazon–X-energy’s 5 GW by 2039), non-nuclear supply agreements (Google–Constellation 2,700 MW), and pending, unsized subscriptions (Oracle–Point Beach) are excluded to avoid double counting.

NOMI. Stage weights are set by Axis Intelligence Research and disclosed above. They rank physical and regulatory distance from delivery; they are not probabilities. Stage assignments cite NRC records where they exist. Limitation: contract prices and termination terms are confidential and are not scored.

2027 snapshot. Counts only deals with a disclosed start date on or before December 31, 2027. Talen’s 2027 ramp volume is undisclosed and is excluded rather than estimated.

About This Dataset

nuclear-energy-for-data-centers.csv holds 16 deal rows, 106 Axis calculation rows and 37 external statistics, each with source organization, document, URL, retrieval date, primary flag and, for calculated rows, the formula. License: CC BY 4.0. Updated when a hyperscaler nuclear contract is announced, when a ledger project changes NOMI stage, or quarterly.

Cite this page

  • APA: Axis Intelligence Research, & Jad, A. (2026, November 3). Nuclear energy for data centers 2026: 14.1 GW of Big Tech nuclear deals tracked. Axis Intelligence. https://axis-intelligence.com/nuclear-energy-for-data-centers/
  • MLA: Axis Intelligence Research, and Aidan Jad. “Nuclear Energy for Data Centers 2026: 14.1 GW of Big Tech Nuclear Deals Tracked.” Axis Intelligence, 3 Nov. 2026, axis-intelligence.com/nuclear-energy-for-data-centers/.
  • Chicago: Axis Intelligence Research and Aidan Jad. “Nuclear Energy for Data Centers 2026: 14.1 GW of Big Tech Nuclear Deals Tracked.” Axis Intelligence, November 3, 2026. https://axis-intelligence.com/nuclear-energy-for-data-centers/.

Related Axis research: Nuclear energy statistics · Uranium price · AI data center tracker · Data center moratorium tracker

Recent Posts

5G Statistics 2026-2027: 3.3 Billion Subscriptions, 59% Coverage and How Much 5G People Actually Use

5G Statistics 2026-2027 By Axis Intelligence Research Co-author: James Porter | Last updated: November 28, 2026 | Licens

Agentic Commerce Trends 2027: AI Agents Own Discovery, Merchants Keep the Checkout, and the Payment Rails Run Ahead of Demand

Agentic Commerce Trends 2027 By Axis Intelligence Research Co-authors: Sarah Davis & Sarah Mitchell | Last updated:

AI Search Trends 2027: Chatbots Lead the Evidence, Agentic Checkout Lags

AI Search Trends 2027 By Axis Intelligence Research Co-authors: Elena Rodriguez & Sarah Mitchell | Last updated: Nov

Axis Intelligence Research

Stay ahead on tech & data

Get notified when we publish or update datasets, trackers, research, and reports across technology, business, AI, cybersecurity, finance, infrastructure, energy, and more.

Research updates only. No spam. Unsubscribe anytime.